Palm oil Factory-1 MWH Battery + 500 kW PCS

- Project Time- February 27th, 2026
- Project Location- Palm Oil Processing Mill
- Some Configurations for this Project
- PCS Specification- 4 units × 125kW Energy Storage Inverter, Total Power 500kW
- Battery Specification- 4 units × 261kWh Liquid-cooled Battery Cabinet, Total Capacity 1044kWh
- Battery Type- Lithium Iron Phosphate (LFP) with BMS
- Controller- SmartGen EMS (Energy Management System)
- MPPT Controller- 63kW MPPT (for PV DC Coupling)
- STS- 250kW Static Transfer Switch for seamless on/off-grid switching
- Some Configurations for this Project
The proposed solution integrates multiple energy sources into a unified, intelligent system:
Solar PV System/ Energy Storage System/ Existing Turbine/ Grid Connection/ Diesel Generator/ EMS Controller

With a clear investment return, the energy storage system requires an initial investment of RM 950,000 and generates annual savings of RM 387,520, resulting in a payback period of just 2.45 years. The system has a design life of over 20 years, delivering more than RM 4.3 million in cumulative savings over 10 years. This solution is also future-proof: while diesel price volatility poses a high risk and any future increases will further shorten the payback period, solar and storage costs remain stable and immune to fossil fuel market fluctuations. Additionally, carbon reduction benefits will continue to grow as the carbon trading market matures.